Nominal Mix Calculator M5-M20 (IS 456 Table 9)

Cement, sand and aggregate for nominal mix concrete M5 to M20 per IS 456:2000 Table 9 mass basis, with conventional 1:2:4-style equivalents and the Cl 9.3

Nominal Mix Concrete Calculator (M5–M20)

Material quantities per IS 456:2000Table 9. Shown in the code's actual mass basis, alongside the conventional 1:2:4-style equivalents sites have batched for decades.

Nominal mix — three proportional containers labelled 1, 2, 4 for cement, sand, and aggregate
Use only for minor works IS 456:2000 Cl 9.3 restricts nominal mixes to plain concrete of M 20 or lower. Structural and reinforced concrete requires a designed mix per IS 10262:2019. Design your mix in the CMD App →

Route 1:

bags cement

Cement
kg
Fine aggregate
kg
Coarse aggregate
kg
Water — maximum
litres

Route 2:

bags ·

Sand
m³
Sand to batch (moist, bulking-corrected)
m³
Coarse aggregate
m³

How this is calculated — and why two answers

IS 456 Table 9 prescribes nominal mixes by mass: total dry aggregate per 50 kg of cement (M5: 800 kg → M20: 250 kg), fine-to-coarse aggregate 1:2 by mass (adjust 1:1½–1:2½ for grading and MSA), and a maximum water content per 50 kg (60 L at M5 down to 30 L at M20). Route 1 converts that batch to per-m³ quantities by absolute volume (cement 3.15, aggregate 2.65 specific gravity).

Route 2 converts the familiar 1:5:10 … 1:1½:3 ratios with the usual 1.54 dry-volume factor. For M5–M10 the two agree closely. For M15 and M20 the conventional ratios run noticeably richer in cement than Table 9: a real divergence you should know about when comparing estimates. We show both rather than quietly pick one.

Verified against IS 456:2000 (AMD 5): see our verified constants table.

Worked example

Given: M20, 1 m³, FA:CA 1:2.

Route 1 (Table 9): one batch = 50 kg cement + 250 kg agg + 30 L water → 0.140 m³ → per m³: 357 kg cement (7.1 bags), FA 594 kg, CA 1189 kg, water ≤ 214 L.

Route 2 (1:1½:3): dry 1.54 m³ → cement 0.28 m³ = 8.1 bags, sand 0.42 m³, CA 0.84 m³.

FAQ

Why can't I select M25 or higher?

IS 456 Cl 9.3 permits nominal (recipe) mixes only up to M20, and only for minor plain works. M25+ needs a designed mix proportioned per IS 10262:2019 for your actual materials, that is what the CMD App does.

Is nominal mix allowed for RCC?

In principle IS 456 restricts nominal mixes to plain concrete minor works. Design mixes are preferred for everything structural; site-batched 1:1½:3 "M20" for RCC is a legacy practice, not a code endorsement.

Why does Route 2 need more cement than Table 9 for M20?

The 1:1½:3 ratio descends from old volume-batched recipes and, converted by mass, sits at about 400 kg/m³ cement versus Table 9's roughly 300 kg/m³. Table 9 is the code's prescription; the ratio is the tradition. For structural work neither replaces a designed mix.

§ 99

Calculator companions

Often used together with this calculator. Pick the next step in your design or QA loop.

Visualisation

This is the same calculator ConcreteInfo publishes on the main site. It runs in your browser, with no account and nothing to install.