Skip to main content

Concrete Sampling Planner — Cube Sets per Pour — IS 456

How many cube samples per pour? IS 456 Cl 15.2.2 frequency table applied to your concrete volume: 75 cubic metres needs 5 samples = 15 cubes

Concrete Sampling Planner

Minimum cube sampling for any pour per IS 456:2000 Cl 15.2.2. Enter the concrete volume of each grade and get the samples,cube count and which acceptance regime applies.

Sampling planner — grid of concrete samples with the selected column highlighted

The frequency is per grade. Run separately for M25 columns and M30 slabs of the same pour.

IS 456:2000 Cl 15.2.2: minimum frequency

1–5 m³1 sample
6–15 m³2 samples
16–30 m³3 samples
31–50 m³4 samples
Above 50 m³4 + 1 per 50 m³ or part

Sampling plan

samples = cubes

Volume entered
m³
Rule applied
Acceptance regime

How this is calculated

The band table of IS 456:2000 Cl 15.2.2 maps concrete volume to minimum samples per grade; above 50 m³ the rule adds one sample per additional 50 m³ or part thereof. Each sample is a set of three 150 mm cubes cast from the same batch per IS 516, so cube count is samples × 3.

The planner also flags which acceptance regime the resulting sample count triggers: fewer than four samples on a pour of 30 m³ or less means Table 11 Note 2 small-pour criteria; four or more means the standard group-of-four check (see the Cube Test Statistics calculator).

Worked example

Given: raft pour of 75 m³ of M30 (run separately for any other grade in the same pour).

75 > 50 → 4 + ⌀((75 − 50)/50)⌁ = 4 + 1 = 5 samples

Cubes = 5 × 3 = 15 cubes. Schedule casting across the pour, sampling randomly from intermediate discharge.

FAQ

Is the sampling rate per pour or per day?

Cl 15.2.2 sets the minimum per quantity of concrete of each grade in the work, in practice evaluated per pour or per defined work section, whichever the QC plan defines. A continuous raft of 130 m³ needs 6 samples even if placed in one shift.

Can I take all cubes from one truck?

No, that samples the truck, not the pour. Sample randomly across the placement: different batches, different points of discharge, and never only the first or last discharge, which are unrepresentative of the bulk.

Why three cubes per sample?

Three cubes from one sample average out specimen-to-specimen variation (compaction, curing) so the recorded strength represents the batch. The set is cast together and tested at 28 days per IS 516; individual cube deviations within a set flag handling or testing problems.

RMC supplier casts their own cubes — do site samples still count?

Producer control cubes verify the plant; site acceptance sampling per Cl 15.2.2 verifies the concrete as delivered and placed. Both matter and they are separate records. Do not substitute one for the other in acceptance decisions.

§ 99

Calculator companions

Often used together with this calculator. Pick the next step in your design or QA loop.

Visualisation

This is the same calculator ConcreteInfo publishes on the main site. It runs in your browser, with no account and nothing to install.

Part of CI-SW-010 Engineering Calculators